Table 20
Port Hueneme Jetties
Port Hueneme, California
Date( s)
Construction and Rehabilitation History
Construction of the harbor along with two jetties (Figure 26) was
Harbor District for a cost of
||content||
,750,000.
completed by the
1940
The east and west jetties were constructed entirely of stone to
lengths of 1,000 ft and 800 ft, respectively.
1968
The existing project (including the jetties) was adopted as a
Federal (civil works) project, and deepening and expansion of the
harbor was authorized. Therefore, the CE assumed maintenance of
the project.
1986
The jetties presently are in satisfactory condition.
PACIFIC
OCEAN
SCALE
200
0
600
Figure 26.
Port Hueneme, California
48