Table 39
Lake Crockett
Whidbey Island, Washington
Date(
Construction and Rehabilitation History
1945
The project was adopted.
The project was constructed, including 28,000 tons of rock for a
1948
breakwater, and the basin and entrance channel were dredged.
1950
The breakwater was repaired.
The breakwater was repaired with 700 tons of rock.
1954
The breakwater was restored to design height and lengthened 175 ft,
1960
and an easterly spur was added for protection against southeasterly
storms. The repair work required 871 tons of rock for the breakwater
plus 505 tons of quarry spalls. An additional 606 tons of quarry
rock were added to a revetment.
The entrance channel was widened to 200
1971
dredging.
The harbor and cross section of the breakwater are illustrated in
1985
No repairs or rehabilitation to the structure have been
recorded since 1960.
155