Table 49
Southport Harbor Breakwater
Southport, Conn.
Date(
Construction and Rehabilitation History
13
88
A 1,320-ft-long rubble-mound breakwater was constructed on the east
side of the Southport Harbor entrance channel (Figure 52). It
appears that the stone construction was tightly interlocked since the
sea and harbor side slopes were approximately
and
respectively. The crown elevation and width were
mlw and
8 ft, respectively.
The breakwater crown was capped with 386 cu yd of concrete, and a
total of 1 3 lin ft of the structure was raised using 1 4 cu yd of
8
8
1976
rubble stone. The capping, 5
wide and 2
thick in cross
section, raised the crown elevation to
inset).
Minor breakwater repairs were made at a cost of 0.
1948
Four damaged sections of the breakwater were repaired by placing
concrete to restore them to a
ft mlw crown elevation, a 5-ft
crown width, and the existing side slopes of adjacent sections.
Approximately 22 cu yd of concrete were used for a total cost of
||content||
,140.
The breakwater was repaired using 0.5- to 3-ton stone and resetting
1958
some existing stone. The stone was placed to a crown elevation of
+ 1 1 ft mlw, a 5-ft crown width, and slopes of
and
on
the harbor and sea sides, respectively. A total of 3,500 tons of
stone were placed for a total cost of ,350.
1960-
During this period, several visual inspections showed the breakwater
was in very good condition.
1978
1982
Annual visual inspection of the breakwater indicated it was in good
condition.
102