Conneaut Harbor Structures
Conneaut, Ohio
Construction and Rehabilitation History
Date
Construction of the east and west piers (Figure 246) was completed.
1894
The piers were constructed of stone-filled timber cribs. (Fig-
ures 246, 247, 248,
and 249 illustrate structures at
Conneaut Har-
bor.) The east pier was 18 ft wide (Figure
and the west pier
was 24 ft wide (Figure 249).
The east and west piers were capped with concrete superstructures
during this period. The east pier had a crest el of
ft
1907
and the west pier superstructure was installed at an el
(Figure 249). The Corps of Engineers presently
of about
ft
maintains o n l y the lakeward 300-ft-long section of the west pier. A
1,054-ft-long portion of the east breakwater (Figure 246, Section
also was constructed during this time. The breakwater was a 23-ft
wide stone-filled timber crib. A concrete superstructure with a
was included along with a rubble slope on
crest el of
ft
)
rubble-mound shoreward extension of the east break-
An
water (Figure 246, Section A) was completed. The extension had a
1912
0
crest el of
ft
tion A ) . Side slopes on the lakeside were
and
on
the harbor side. Armor stones greater than 3 tons each were used in
construction.
A 3,403-ft-long rubble-mound west breakwater (Figure 246, Sections A
and I was constructed during this time. Breakwater c r o s s sections
)
1917
were similar to those used for the east breakwater extension built
Construction of an 886-ft-long rubble-mound lakeward extension of the
east breakwater (Figure 246, Section B) was completed during this
1923
time. The structure cross section was similar to the shoreward ex-
tension of the east breakwater completed during 1911-1912 (Fig-
)
Construction of a 935-ft-long rubble-mound lakeward extension of the
an 865-ft-long rubble-mound
1936
lakeward extension of the west breakwater (Figure 246, Section
and a
rubble-mound shore arm of the west breakwater
(Figure 246, Section H) was
completed. The lakeward extensions had
10-ft crest widths and crest els of
ft
F and G. Side slopes were
and armor stone had a minimum
)
weight of 3 tons with not less than 50 percent of 5 tons or more.
(Continued)
364