Muskegon Harbor Structures
Muskegon, Michigan
Construction and Rehabilitation History
1868-
Construction of a 703-ft-long north pier and a 692-ft-long south
1890
pier (Figure 130) was completed during this time. The piers were
originally built with woodpilings and ranged from 18 to 32 ft in
width. The area between the pilings was filled with stone and tim-
ber, and the piers were capped with a timber superstructure.
1906
The north pier was rebuilt with timber pilings similar to the origi-
nal construction.
1927-
Construction of the north and south breakwaters (Figure 130) was
1931
Muskegon Harbor.) The north breakwater was a rubble-mound structure
that was capped with 8- to 10-ton
(Figure 132, Sections A and
armor stone (Section A) with the exception of the shoreward end (Sec-
tion
which had 1- to
armor protection. The crest el of the
structure was about
ft lwd, and side slopes were
The
lakeward portion of the south breakwater (Figure 132, Sections C , D,
and E was constructed with stone-filled concrete caissons on wood-
)
pilings. These structures had concrete caps that were 7.3 ft wide at
ft lwd. The shoreward portion of the
the crest with an el of
south breakwater (Figure 132, Sections F, G, and
was composed of
woodpiling with a stone fill and concrete and stone superstructures.
The structures ranged from 14 to 17 ft in width and had crest els
to
ft lwd. The outer 54 ft of the south
ranging from
breakwater consisted of two rectangular stone-filled concrete
side slope was placed along the
caissons. Riprap with a
sides of most of the structure.
The north and south pier superstructures were rebuilt and consisted
1932-
of concrete and stone construction (Figure 131, Sections N, 0, and
1934
During this period a total of 16,757 tons of riprap stone was placed
1942-
along the sides of the south breakwater (Figure 132, Sections C, D,
1954
E, F, and G ) .
An additional 4,832 tons of riprap was placed along the south break-
1960-
water at Sections E and F (Figure 130).
1963
The south pier (Figure 130, Sections N, 0, and P) was rehabilitated
1966
by encasing it in steel sheetpiling. The voids were filled between
the sheetpiling and the existing structure, and the pier was capped
with concrete. The new el was
ft lwd, and the width ranged from
35 to 45 ft. A portion of the south breakwater (Figure 130, Sec-
tions F and G was rehabilitated also. Fill-stone replenishment and
)
regrouting of the superstructure was accomplished, and additional
riprap stone was placed along the shoreline.
(Continued)
21 1