Table 2
Two,Harbors Breakwaters
Two
Date
Construction and Rehabilitation History
Construction of a 900-ft-long stone-filled timber crib breakwafer
1893
(Figure 7, Sections C, D, and E) was completed at the site. The
cribs were built on rubble-mound foundations. The easternmost 800 ft
of the structure was 24 ft wide (Figure 8, Section C), the adjacent
50-ft portion was 20 ft wide (Figure 8, Section D), and the
most 50 ft of the breakwater was 16 ft wide (Figure 8, Section E .
)
A concrete cap (superstructure) was built on the breakwater.
The
ft lwd (Figure 8, Sections C, D, and E .
)
crest el was
1934
A
stone-filled timber crib breakwater on a rubble-mound
base was constructed (Figures 7 and 8, Section B). The structure was
1949
30 ft wide. The rubble-mound base consisted of 5-ton cover stone on
side slopes.
Construction of a 326-ft-long rubble-mound shore connection of the
1948
east breakwater was completed (Figures 7 and 8, section A ) . The
crest was 12 ft wide with a
ft crest el.
A concrete cap (superstructure) was built on the 1,302-ft-long break-
The
water that was completed during 1947-49 (Figure 8, Section
1950
crest el of the structure was increased to
ft.
Since construction, records indicate that localized damage of the
1986
breakwaters has occurred and has been repaired during routine main-
tenance. The structures are presently in good condition.
23
I