Table 1 (Concluded)
Date
Construction and Rehabilitation History
additional stone to raise the el in some locations above the water
level. The concrete cap of the west breakwater was noted shifting,
cracking, separating, and/or tilting in some locations. Concrete
spalling also was noted.
The general condition of the east and west breakwaters is considered
1986
fair. The rubble-mound inner breakwater is in good condition.
20