Laboratory Testing
Laboratory testing of Portadam, HESCO Bastion concertainer, RDFW, and sandbag
structures was conducted in a wave research basin at ERDC. The products were tested in a
controlled laboratory setting but under conditions that emulate real world flood fighting. The
structures were tested consecutively under identical conditions. Stringent construction, testing,
and removal protocols were developed for the laboratory. The protocol for the laboratory testing
included both performance parameters (hydrostatic testing, hydrodynamic testing with waves and
overtopping, and structural debris impact testing with a floating log) and laboratory setting
operational parameters (time, manpower, and equipment to construct and disassemble, suitability
for construction and disassembly by unskilled labor, fill requirements, ability to construct around
corners, disposal of fill material, damage, repair, and reusability).
The laboratory testing included the construction of skewed u-shaped structures. Each
structure had an approximate length of 85 ft. Due to the restrictive height of the research basin
walls, the height of each structure was limited to approximately 3 ft. Laboratory testing of the
structures was initiated in March 2004 and completed during August 2004. The sandbag structure
was tested first in the laboratory followed in order by the HESCO Bastion concertainer structure,
the RDFW structure, and finally, the Portadam structure.
Laboratory Testing Results
Tables 1 through 3 present a summary of pertinent laboratory testing results. The results show
that as expected, the sandbag structure took much longer (205.1 man-hours) to construct than the
other three structures. Only Portadam was removed in less time than required to remove the
sandbags, largely because all structures other than sandbags were largely reusable and required
care in their removal. The sandbag levee was the only structure to fail during any of the tests.
Table 1 gives a summary of man-hrs to construct and remove each structure. Details of the
construction are given in Table 4, and details of the removal are given in Table 5.
Each structure was allowed a maximum of three repairs at specified times during the testing
sequence, with each repair limited to a maximum of four man-hrs. In addition, one rebuild of the
structure was allowed. Only the sandbag levee required a rebuild. A summary of the man-hrs
required for repairs on each structure is given in Table 1, and details of each repair are given in
Table 6.
Seepage rates through the sandbag levee were very low during the one foot hydrostatic head
test because the sandbag levee is wide at the lower portion of the levee. Seepage rate increased
through the sandbags as the water elevation rose and the levee became narrower. Sandbags had a
particularly high "seepage" rate during dynamic tests with large waves because waves were able
to run up the sloped face of the levee and overtop the structure. Seepage rates during the static
head tests are given in Table 2.
Seepage rates for both RDFW and Portadam were generally much lower than for the sandbag
levee. Seepage rates for HESCO Bastion were considerably higher than sandbags, with most of
the seepage flowing through the junction between adjacent units. It was later determined that the
local HESCO office was not familiar with HESCO-recommended construction techniques for use
of the concertainers as a flood barrier that should significantly reduce the seepage between units.