Table 72 (Concluded)
Construction and Rehabilitation History
Date
Riprap was replenished along portions o f the north breakwater, and
1981
cracks in the superstructure were repaired.
An inspection of the site indicated the structures are in need of
1985
major rehabilitation. The timber cribbing of the substructures is
collapsing under the weight of the concrete superstructures resulting
in shifting and cracking of the superstructure. The breakwaters are
considered to be in poor condition, and major rehabilitation has been
VICINITY MAP
Figure 1 9 2 .
Harbor Beach, Michigan
295