Construction and Rehabilitation History
existing structure and the steel sheetpiling were filled with stone
and the area capped with concrete.
Construction of a new north pier head and repair of the adjacent
1958
and K) was com-
pleted, The pier head consisted of a circular steel sheet-pile cell
with a diameter of 23.75 ft. The cell was stone filled and capped
with concrete to an el of
ft, and riprap was placed around its
slope, Section K was encased in steel sheet-
base on a
piling (Figure 154). Voids were filled with stone, and the area be-
tween the existing pier and the new steel sheetpiling was capped with
concrete at an el of
ft lwd. The new pier width was 33 ft.
The shoreward portion of the north pier (Figure 153, Sections
1960-
and L) was encased in steel sheetpilings (Figure 154) resulting in a
1961
new pier ranging from 29.75 ft (Section
to 33 ft (Section
in
width. The voids between the new steel sheetpiling and the existing
piers was filled with stone and capped with concrete (Figure 154).
The shoreward portion of the south breakwater (Figure 153, Sec-
1966
tions F , G, H, and I was rehabilitated. Rehabilitation consisted of
)
the placement of stone along the structures (Figure 155) on slopes of
Cover stone ranged from 9 (min) to 12 tons
along Sec-
tion F, 6 (min) to 8 tons (max) along Section G, and 3.5
to
5.5 tons
(max) along Section H (Figure
155) on both sides of the
breakwater. Riprap (1 ton) cover stone was installed on the lakeside
only of Section I
.
Portions of the north breakwater (Figure 153, Sections D and E were
)
1977
replenished with fill stone, and the structure was grouted over with
concrete.
1981
Riprap stone was placed around the heads of both the north and south
)
The lakeward end of the south
was repaired by encasing it in
steel sheetpiling (Figure 154, Sections N and N-1). Voids between
the existing pier and new steel sheetpiling were filled with stone
ft lwd. Sec-
which was covered with a concrete cap at an el of
tion N was 30 ft wide, and Section
1982
The landward portion of the south pier (Figures 153 and 154, Sec-
tion 0) was repaired, and riprap was placed on the channel side of
side slopes. Fill stone also was replenished
the pier with
(Continued)
(Sheet 2 of 3)