Table 44 (Concluded)
Construction and Rehabilitation History
Date
The landward portions of the north and south piers (Figure 114, Sec-
1940
tion A) were capped with stone and concrete superstructures resulting
of
)
in pier crest
ft
The entire north pier (Figure 114) was repaired during this time
1962-
1963
frame. Repairs consisted of installing steel sheetpiling on each
side of the existing structures, filling the voids with stone, and
capping the structure with concrete. Widths of the pier ranged from
31.5 to
1964-
A 179-ft portion of the south pier (Figure 1 1 4 , Section J) was re-
constructed. Steel sheetpiling was installed on each side of the
1965
existing pier forming a 32.7 ft-wide structure (Figure 116, Sec-
tion J. The voids were filled with stone, and a concrete cap was
)
installed.
1970-
Additional portions of the south pier (Figure 1 1 4 , Sections H,
1972
K, K2, and
were repaired during this period. These piers were
repaired similar to the earlier ones by the installation of steel
sheetpiling on each side of the existing pier. Voids were again
stone filled and the structure capped (Figure 116, Section H; and
K, K2, and L ) . Widths of the rehabilitated
structure sections ranged from 30 to 42 ft.
Riprap ranging from 1 to 6 tons was placed along the lakeside face of
1981
the north pier (Figure 114, Section A. Approximately 1,788 tons of
)
stone was used that extended from the head of the pier 600 ft shore-
ward. Also, 38 tons of 2- to 4-in. stone was placed under the caps
to replenish fill stone.
Approximately 1,029 tons of riprap was placed along the north pier
1982
(Figure 114, Sections A and B) and 2,054 tons along the south pier
(Figure 114, Section A . Three- to sixteen-ton
stone was used for
)
the purpose. Additionally, 40 tons of 1- to 3-ft stone was placed
under the caps of the south pier to replenish fill stone.
About 600 tons of 6- to 12-ton riprap was placed along the lakeside
1983
of the north pier shoreward of the riprap placement of 1981 and 1982.
An inspection of the structures revealed that the north pier was in
1985
good
tion A)
stable and in fair condition. Separation, settle-
ment, and cracking of the superstructure was noted, and maintenance
repairs have been recommended. The remaining portions of the south
pier were in good to excellent condition. An aerial view of the
South Haven Harbor piers is shown in Figure 118.
190