Table 12 (Concluded)
\
Date
Construction and Rehabilitation History
at various locations on both piers, and it was noted that the con-
crete superstructure had spalled in areas. In the summer of this
year, core and cover stone were placed where necessary to repair the
structures.
1986
The piers presently are in fair condition. An aerial view of
Ontonagon Harbor piers is shown in Figure 30.