Table 22
Bakers Haulover Inlet Jetties
Bakers Haulover Inlet, Florida,
Construction and Rehabilitation History
1925
A man-made inlet was constructed by local interests.
Existing steel sheet-pile jetties (private construction, date
I
1964
unknown) had rusted through, and wave action had partially removed
sand fill behind them. Loss of this fill caused the collapse of
portions of an 8-in. concrete cap on both jetties. The sheet-pile
jetties were removed and 150-ft-long rubble-mound jetties were con-
6 . The jetty section
consisted of
1,500- to 2,500-lb and 8- to 12-ton stone for the core and cap,
respectively. 12-ton minimum cap stone was placed on the outer
with a crown width
50 ft of the jetties. The side slopes were
and elevation of 1 ft and
0
ft mlw, respectively. The design was
based on a wave height of 14 ft and Hudson's slope stability
The centerline distance between the jetties was about 415 ft,
the south jetty being placed about 100 ft south of the sheet-pile
jetty. The channel was dredged to -11 ft mlw. Total cost of the
jetties and connecting revetments was 7,000.
1974
interests
Harbour
The south jetty was extended by
Village, no details) with subsequent reimbursement of applicable
extension consisted of an armor
Federal share of costs. The
stone jetty capped with concrete. The seaward end curves 90 deg
(quarter circle) away from the inlet.
1985
The north jetty was essentially rebuilt to act as a sand-tight
minal groin since the existing jetty would not be effective in main-
taining the planned beach renourishment north of, and adjacent to,
the jetty. Prior to being rebuilt, an inspection indicated that the
jetty had held up well since its construction but that it was inef-
fective in retaining sand which passed through it and around its
seaward end. A general design
describes the rebuilt
have occurred) as
jetty (though it appears some design
concrete block has been added to the jetty section,
follows:
which has decreased the amount of rock required substantially." The
525-ft-long north jetty had a 425-ft section parallel to, and approx-
imately 30 ft north of, the old
and a perpendicular section at
the seaward end extending away
ft mlw
the 425-ft section decreased
The crest elevation of
to 7 ft between the "heel" and "toe" of the 100-ft section. A crest
width of 21 ft extended over the innermost 250 ft, decreased to
16 ft at the heel, and then remained constant out to the toe. Side
The jetty section was made up of three layers;
slopes were
of 1- to 12-in. stone, and
the innermost core and foundation
stone layers, an underlayer of
and a cover layer of 6- to 12-ton stone. Concrete grout was placed
along the inner 300 ft of the jetty, over 15 ft of the crest width,
(Continued)
65